CENTRUMPLAN BEDUM PRESENTATIE BELANGHEBBENDEN 03-04-2017
CENTRUMPLAN BEDUM ONTWERPPROCES OPENBARE RUIMTE TECHNISCHE UITWERKING TECHNISCHE UITWERKING
CENTRUMPLAN BEDUM ONTWERP RIOLERING UITGANGSPUNTEN NIEUWE RUIMTELIJKE INRICHTING WIJZIGINGEN CENTRUMGEBIED en BEDERAWALDA KLIMAATBESTENDIG ONTWERP RIOOLSTELSEL GESCHEIDEN RIOOLSTELSEL VERSTERKEN AFWATERING OPENBARE RUIMTE BEHOUDEN/ UITBREIDING WATERSTRUCTUUR CENTRUMGEBIED
CENTRUM PLAN BEDUM ONTWERP RIOLERING RECONSTRUCTIE RIOLERING DE VLIJT EN KERKLAAN Kerk Bakker Slijter Gymzaal Groenteboer Slager Huisarts Vlijtzicht Bederawalda (oudbouw)
CENTRUM PLAN BEDUM ONTWERP RIOLERING RECONSTRUCTIE RIOLERING DE VLIJT EN KERKLAAN Togtemaarschool
CENTRUMPLAN BEDUM AANLEG RIOLERING UITGANGSPUNTEN VRIJMAKEN KERKPLEIN t.b.v. GEZONDHEIDSCENTRUM WIJZIGEN KABELS & LEIDINGEN/RIOLERING AANLEG GESCHEIDEN RIOLERING VERSTERKEN AFWATERING OPENBARE RUIMTE BEHOUDEN/ UITBREIDING WATERSTRUCTUUR CENTRUMGEBIED GEFASEERDE UITVOERING WERKZAAMHEDEN BEREIKBAARHEID ONDERNEMERS BEHOUDEN MARKT IN HET CENTRUM
CENTRUMPLAN BEDUM FASERING AANLEG RIOLERING
CENTRUMPLAN BEDUM FASERING AANLEG RIOLERING UITGANGSPUNTEN BEREIKBAARHEID WINKELS EN WONINGEN BORGEN HUIDIGE KERKPLEIN GEBRUIKEN VOOR OMLEIDING GEEN VRACHTVERKEER DOOR GROTESTRAAT en KERKLAAN, LIJNBAAN en VRIJE GANG, BAZUINSLAAN DE MARKT VERPLAATST TIJDELIJK
CENTRUMPLAN BEDUM FASERING AANLEG RIOLERING
CENTRUMPLAN BEDUM FASERING AANLEG RIOLERING UITVOERING AFSPRAKEN MAKEN MET DE ONDERNEMERS OVER DE UITVOERING START UITVOERING EIND MEI BEGIN JUNI 2017 WERKZAAMHEDEN PER FASE UITVOEREN COMMUNICATIE TIJDENS UITVOERING MET DE TOEZICHTHOUDER BEREIKBAARHEID LEVERANCIERS EN KLANTEN STAAT VOOROP EIND SEPTEMBER UITVOERING GEREED
CENTRUMPLAN BEDUM FASERING PROJECTEN PROJECTENPLANNING KERN BEDUM RECONSTRUCTIE DE VLIJT (fase 1) 2017 RECONSTRUCTIE DE VLIJT (fase 2) 2017/2018 RECONSTRUCTIE BOTERDIEP Oz 2017 RECONSTRUCTIE WALDADRIFT 2018 VOLGORDE BELANGRIJK i.v.m. BEREIKBAARHEID EN ONTSLUITING
CENTRUMPLAN BEDUM FASERING PROJECTEN RIOOLRECONSTRUCTIE DE VLIJT (FASE 1) UITVOERING: JUNI t/m SEPTEMBER 2017
CENTRUMPLAN BEDUM FASERING PROJECTEN RIOOLRECONSTRUCTIE DE VLIJT (FASE 2) UITVOERING: SEPTEMBER 2017 t/m APRIL 2018
CENTRUMPLAN BEDUM FASERING PROJECTEN RECONSTRUCTIE BOTERDIEP Oz. UITVOERING: GEREED VOOR EIND JULI 2017
CENTRUMPLAN BEDUM FASERING PROJECTEN RECONSTRUCTIE WALDADRIFT UITVOERING: MEI 2018 t/m DECEMBER 2018
CENTRUMPLAN BEDUM PRESENTATIE BELANGHEBBENDEN 03-04-2017 VRAGEN