De presentatie wordt gedownload. Even geduld aub

De presentatie wordt gedownload. Even geduld aub

De Stroomversnelling Heerhugowaard

Verwante presentaties


Presentatie over: "De Stroomversnelling Heerhugowaard"— Transcript van de presentatie:

1 De Stroomversnelling Heerhugowaard

2 W&R-Renovatie Pillars
Concepts based on reference houses, manage the differences (80:20) Co-makers ( preferred subcontractors and suppliers ) The resident is the starting point of decision making Process-driven collaboration W&R-Renovatie is based on the same principles as W&R. Next slide Clear Which means with every decision, we ask ourselves what value does it add for the resident. In the end, at least 70% of the residents need to agree with the plan, this right they have by dutch law.

3 The potential of the market in NL
The concepts of W&R-R are based on a number typical homes for a certain period of construction. For each reference we develop different renovation concepts. The different concepts are based on the strategy of the housingcorporation each depending on the extention of the exploitation period – years and for the Stroomversnelling concept 40 years. The concept that is the focus of the presentation is a transformation to energy neutral for reference 2. A terraced house that is built between 1946 en 1986.

4 Collaboration ‘De Stroomversnelling’
The concept of DSV is based on a number typical homes, comparable to the reference houses just mentioned. Within the Stroomversnelling there’s a collaboration between 6 housingcorporations and 4 large construction companies. According to the performance requirements each company is developing its own concept. Its best described as each company is producing coffee, but with its own flavour.

5 The challenge ‘De Stroomversnelling’
DBM-contract Energy neutral Renovation within 10 working days Residents remain in their homes Addtitional 40 year lease Movie : NOM The challenges of the assignment of the stroomversnelling are; The house should be resotored to an energy neutral level, which means a single house must produce as much energy a year as a regular family uses a year. The renovation must take place within 10 working days. Because of an additional renovation of the kitchen, bathroom and toilet in this case the renovation takes working days. It must be possible for the resident to remain in their home. After the renovation it must be possible for the client to keep the house in the market of lease for another 40 years. During the 40 years BAM is responsible for the maintenance of the house

6 Resident participation , 100% agreement
BAM takes responsibility for the resident participation. By Dutch law the tenants have to agree with the renovation plan. Normally a 70% agreement would be necessary. In this case a 100% agreement is necessary. This is because of the funding of the project ( explain later ). How do we do this: Started with a prototype , renovate 1 terraced house. Invite residents to come over and have a look and feel Ask them for agreement Explain details in a residents evening. By presenting and a brochure I’m responsible for the communication with the residents during the preparations of the project. From my own experince I can tell that ; Above all its important that the plan meets the needs and expectations of the residents. They are usually not so interested in the type of heatpump they get, but more into the different colours they can chose for their new IKEA kitchen.

7 Energyservice = + + Now After renovation € now,,- € just now,- Rent
Rent Rent Servicecost Servicecost Energyservice Energycost + + = € now,,- € just now,-

8 Reference 2 - Heerhugowaard
Characteristics Terraced house Brick facade with cavity Wooden floors m2 Inclining roof with tiles The main characteristics of a reference 2 house are; Brick facade with cavity Wooden floors , in this case the house had a concrete ground floor m2 Big windows at both front and back facade ( doorzon-through room ) – house with a through room Inclining roof with tiles 3 sleepingrooms , 1 bathroom , in this case an extra room in the attic

9 Prototype #1 Heerhugowaard
Main concept: Prefabricated timber frame construction (HSB) facade. Level of prefabrication includes ; windowframes, windows, cladding, mineral brickstrips Prefabricated roof : level of prefabrication includes; mounting brackets of the solar panels Energy-module : a 1,5m2 unit which includes all new installation necessary for the house ; heatpump, ac-dc converter, balanced ventilation system with heat recovery. Insulation of the groudfloor (crawl space) with drowa chips Retrofit of the kitchen, bathroom and toilet ( explain later in detail ) 9

10 3D Scanning and BIM BIM To make this project possible we worked with 3d scanning. External facades are first scanned using a 3D laser scanner. After that a detailed point cloud is generated. This forms the basis of a BIM model into which subcontracters add their objects; facades, roofing elements. We then examine junctions and other details to resolve conflits. To complete the project within this short amount of time and while residents stay in their homes we have to pre-manafacture. Doing the 3D scans makes it much easier to design and fit all the new components in the existing situation. Although we are woring on terraced housing, a separate model is requierd for eacht home, as windows on older properties are not always at the same width of height. Even though the roof might look straight, over the entire terrace it can deviate by up tot 10cm. Conecting details are designed in such a way that they can take some measurement tolerances.

11 Energiemodule Energiemodule 0.1 prototype Energiemodule 0.2 protoblok
One of the new developments i like to point out is the Energiemodule. As explained it contains all installation components necessary for the house. All components are transported to one of our co-makers. Which is responsible for assembling all parts. The heatpump is programmed and tested. The Energiemodule is placed at the back against the facade, because the components are already installed we have the house transformed from its traditional installationsystem to the new sustainable installation system in a short amount of time. From the 1st prototype to the 3rd. The energiemodule was reduced in size, price and made easier suitable for maintenance. Energiemodule 0.2 protoblok Energiemodule 0.3 projectscale

12 Construction proces Movie : Timelaps

13 Preparations Set up dimensions and insultion below ground level ( outside crawl space ) 20 cm deep trench

14 Day 1 Demolition interior ( BKT )
Demolition interior ( bathroom , kitchen, toilet )

15 Day 2 Premounting The pre mounting / rough cut of the waterpipes in bkt, ventilation tubes, electricity in bkt

16 Day 3 Cast floor – layer 1 On top of the old bathroom and toilet floor we make a new cast floor. This system is choosen because we don’t need to take down the old floor. This will safe us a lot of dust and waste

17 Day 4 Cast floor – layer 2

18 Day 5 Glass panels and plumbing
The glass panels are placed for along the old tiles. This system is chosen because usualy there are allready 2 layers of tiles, which means we have to get rid of both layers. Placing of the glass panels is quicker and therefore causes less inconvenience for the residents. Besides the advantages during construction the maintenance and durability of the glass panels is also better then for tiles.

19 Day 6 Kitchen New kitchen from IKEA, which contains cooking plate for induction.

20 Day 7 Facade

21 Day 7 Energiemodule

22 Day 8 Roof

23 Day 9 Solar panels

24 Day 10 Insulation crawl space

25 Day 10 Result

26 Questions


Download ppt "De Stroomversnelling Heerhugowaard"

Verwante presentaties


Ads door Google