CENTRUMPLAN BEDUM PRESENTATIE BELANGHEBBENDEN 03-04-2017
2
CENTRUMPLAN BEDUM ONTWERPPROCES OPENBARE RUIMTE
TECHNISCHE UITWERKING TECHNISCHE UITWERKING
3
CENTRUMPLAN BEDUM ONTWERP RIOLERING
UITGANGSPUNTEN NIEUWE RUIMTELIJKE INRICHTING WIJZIGINGEN CENTRUMGEBIED en BEDERAWALDA KLIMAATBESTENDIG ONTWERP RIOOLSTELSEL GESCHEIDEN RIOOLSTELSEL VERSTERKEN AFWATERING OPENBARE RUIMTE BEHOUDEN/ UITBREIDING WATERSTRUCTUUR CENTRUMGEBIED
4
CENTRUM PLAN BEDUM ONTWERP RIOLERING
RECONSTRUCTIE RIOLERING DE VLIJT EN KERKLAAN Kerk Bakker Slijter Gymzaal Groenteboer Slager Huisarts Vlijtzicht Bederawalda (oudbouw)
5
CENTRUM PLAN BEDUM ONTWERP RIOLERING
RECONSTRUCTIE RIOLERING DE VLIJT EN KERKLAAN Togtemaarschool
6
CENTRUMPLAN BEDUM AANLEG RIOLERING
UITGANGSPUNTEN VRIJMAKEN KERKPLEIN t.b.v. GEZONDHEIDSCENTRUM WIJZIGEN KABELS & LEIDINGEN/RIOLERING AANLEG GESCHEIDEN RIOLERING VERSTERKEN AFWATERING OPENBARE RUIMTE BEHOUDEN/ UITBREIDING WATERSTRUCTUUR CENTRUMGEBIED GEFASEERDE UITVOERING WERKZAAMHEDEN BEREIKBAARHEID ONDERNEMERS BEHOUDEN MARKT IN HET CENTRUM
7
CENTRUMPLAN BEDUM FASERING AANLEG RIOLERING
8
CENTRUMPLAN BEDUM FASERING AANLEG RIOLERING
UITGANGSPUNTEN BEREIKBAARHEID WINKELS EN WONINGEN BORGEN HUIDIGE KERKPLEIN GEBRUIKEN VOOR OMLEIDING GEEN VRACHTVERKEER DOOR GROTESTRAAT en KERKLAAN, LIJNBAAN en VRIJE GANG, BAZUINSLAAN DE MARKT VERPLAATST TIJDELIJK
9
CENTRUMPLAN BEDUM FASERING AANLEG RIOLERING
10
CENTRUMPLAN BEDUM FASERING AANLEG RIOLERING
UITVOERING AFSPRAKEN MAKEN MET DE ONDERNEMERS OVER DE UITVOERING START UITVOERING EIND MEI BEGIN JUNI 2017 WERKZAAMHEDEN PER FASE UITVOEREN COMMUNICATIE TIJDENS UITVOERING MET DE TOEZICHTHOUDER BEREIKBAARHEID LEVERANCIERS EN KLANTEN STAAT VOOROP EIND SEPTEMBER UITVOERING GEREED
11
CENTRUMPLAN BEDUM FASERING PROJECTEN
PROJECTENPLANNING KERN BEDUM RECONSTRUCTIE DE VLIJT (fase 1) 2017 RECONSTRUCTIE DE VLIJT (fase 2) 2017/2018 RECONSTRUCTIE BOTERDIEP Oz 2017 RECONSTRUCTIE WALDADRIFT 2018 VOLGORDE BELANGRIJK i.v.m. BEREIKBAARHEID EN ONTSLUITING
12
CENTRUMPLAN BEDUM FASERING PROJECTEN
RIOOLRECONSTRUCTIE DE VLIJT (FASE 1) UITVOERING: JUNI t/m SEPTEMBER 2017
13
CENTRUMPLAN BEDUM FASERING PROJECTEN
RIOOLRECONSTRUCTIE DE VLIJT (FASE 2) UITVOERING: SEPTEMBER 2017 t/m APRIL 2018
14
CENTRUMPLAN BEDUM FASERING PROJECTEN
RECONSTRUCTIE BOTERDIEP Oz. UITVOERING: GEREED VOOR EIND JULI 2017
15
CENTRUMPLAN BEDUM FASERING PROJECTEN
RECONSTRUCTIE WALDADRIFT UITVOERING: MEI 2018 t/m DECEMBER 2018
16
CENTRUMPLAN BEDUM PRESENTATIE BELANGHEBBENDEN 03-04-2017
VRAGEN